# 53.10 - level 1 internal cross bracing connector

---

# Overview

See [3D overview of 53.10](https://a360.co/44T5xxY)

## Assembled view

Assembled 53.10

## Exploded view

Exploded-view of 53.10

# Parts

See order of use for [53.10 - level 1 internal cross bracing connector](https://cloud.instock.com/assets/articles/53.10/manual/)

# Assembly steps

These are assembly instructions for adding fasteners to a connector adaptation. Before adding fasteners the following are prerequisites:

1. the slab is level
2. baseplate connector is staged per layout
3. sandwich panels are staged

Initial position state of 53.10

## Step 1

Position 2 pcs. of [4.11 shim for baseplate connector](https://cloud.instock.com/assets/articles/4.11/) in such a way that they ensure uniform levelness across all connectors on the first level.

## Step 2

Drill holes at the designated points, then proceed to securely install 4 pcs. [99.15 anchor 3/8-16](https://cloud.instock.com/assets/articles/99.15/) in these holes.

## Step 3

Insert 4 pcs. of [1.5 plywood washer](https://cloud.instock.com/assets/articles/1.5/) into sandwich panel holes.

## Step 4

Position 2 pcs. of [10.15 floor plate with countersunk holes](https://cloud.instock.com/assets/articles/10.15/) as depicted in the picture above.

## Step 5

Fasten floor plates with 8 pcs. of [99.73 countersunk screw](https://cloud.instock.com/assets/articles/99.73/) in designated holes for countersunk screws.

## Step 6

Position [15.56 cross bracing bracket](https://cloud.instock.com/assets/articles/15.56/) as depicted on the image.

## Step 7

Add 4 pcs. of [99.91001 washer](https://cloud.instock.com/assets/articles/99.91001/) onto the screws and fasten with 4 pcs. of [99.13 hex nut](https://cloud.instock.com/assets/articles/99.13/).