Instock · 53.10 - level 1 internal cross bracing connector

53.10 - level 1 internal cross bracing connector


Overview

See 3D overview of 53.10

Assembled view

Assembled 53.10

Exploded view

Exploded-view of 53.10

Parts

See order of use for 53.10 - level 1 internal cross bracing connector

Assembly steps

These are assembly instructions for adding fasteners to a connector adaptation. Before adding fasteners the following are prerequisites:

  1. the slab is level
  2. baseplate connector is staged per layout
  3. sandwich panels are staged

Initial position state of 53.10

Step 1

Position 2 pcs. of 4.11 shim for baseplate connector in such a way that they ensure uniform levelness across all connectors on the first level.

Step 2

Drill holes at the designated points, then proceed to securely install 4 pcs. 99.15 anchor 3/8-16 in these holes.

Step 3

Insert 4 pcs. of 1.5 plywood washer into sandwich panel holes.

Step 4

Position 2 pcs. of 10.15 floor plate with countersunk holes as depicted in the picture above.

Step 5

Fasten floor plates with 8 pcs. of 99.73 countersunk screw in designated holes for countersunk screws.

Step 6

Position 15.56 cross bracing bracket as depicted on the image.

Step 7

Add 4 pcs. of 99.91001 washer onto the screws and fasten with 4 pcs. of 99.13 hex nut.